Old made new: the 4-seater chairlift “Einzeiger” in Sölden was in operation until spring 2025. After 27 years it was dismantled and replaced by a modern 8-seater chairlift.
Following expert inspection by the ropeway manufacturer and TÜV Süd, and a positive construction hearing, the old “Einzeiger” is now becoming the new Freda 4-seater chairlift in the Montafon. Both ropeway stations and 10 of the 11 towers in total could be fitted into the new terrain at the design stage.
The bottom station has already been re-erected and gleams as good as new.
The service building next to the ropeway station is already clearly recognisable, and the walls of the new chair garage are currently going up as well.
Progress on site at a glance
Early July 2026: at the top station the striking summit in the background is always worth a snapshot – the Fredakopf, which gives the planned Freda Bahn its name. The old 2CLF Fredakopf installation is still standing here.
Mid-July 2026: not much is left of the old installation – demolition on a grand scale to make room for something new.
Early August 2026: the new site is taking shape. A material ropeway handles all the transport – formwork, reinforcement and concrete included.
Early September 2026: work is progressing quickly – the same view one month later.
Project management, text and photos: Katrin Mangeng