The excavators move in: a new 4-seater chairlift for the Wurbauerkogel

Over seven minutes of ride time, room for one person and hardly any capacity for bikes: the old single chairlift on the Wurbauerkogel is now gone for good. Two weeks ago the excavators moved in and began demolishing the old bottom station. On 11 November 2026 the construction hearing under ropeway law followed. From May 2027, a modern detachable 4-seater chairlift will carry guests and bikes to the summit in 4.3 minutes.

The starting point
Until now, a single chairlift ran up the local mountain of Windischgarsten in Upper Austria. It was around 890 m long and managed a maximum of 500 persons per hour with a ride time of more than seven minutes. Because the installation was old, needed a great deal of maintenance and spare parts were barely available any more, it was taken out of service. A general overhaul would no longer have paid off economically. Traunsee Touristik GmbH Nfg. & Co KG therefore decided on a new build.
The project
Salzmann Ingenieure is designing the new detachable 4-seater chairlift from Doppelmayr for Traunsee Touristik. It has two jobs:
- Lap lift for the bike park: every second chair is a bike carrier for three bikes.
- Feeder for day visitors to the viewing platform at the summit
The bottom station is being built on the site of the previous bottom station. The top station will be built around 10 m further north.
The new lift at a glance
- System type: detachable 4-seater chairlift with weather protection bubbles
- Vertical rise: 235 m (623 to 858 m a.s.l.)
- Slope length: 865 m
- Towers: 8
- Line speed: 4 m/s, ride time 4.3 minutes
- Capacity in bike operation: 447 persons and 335 bikes per hour
- Capacity in pedestrian operation: up to 1,284 persons per hour
- Drive: top station, return/tension station at the bottom station
- Commissioning: May 2027
What the new lift delivers
Guests will travel in far greater comfort: padded chairs, weather protection, a smooth ride and easier, more accessible boarding and unloading. Waiting times will be shorter, above all for bikers at weekends. Modern drive and safety technology will keep the lift running more reliably in wind and bad weather. In this way the lift strengthens tourism in the region.


What happens next?
Once demolition is complete, construction work on the new stations and towers will begin. The new lift is due to enter service in May 2027. We will keep you posted on progress on site.
Projects like this one show what ropeway design is all about: replacing an old installation with a lift that works equally well for bikers, families and day visitors. We support the whole process, from preliminary design through permit submission and the construction hearing to construction supervision on site. Is a new build or a replacement coming up for your installation? Find out more about our ropeway design and our reference projects – we look forward to your project.
We are already looking forward to riding the new chairlift up the Wurbauerkogel with our bikes next summer!
Project manager: Stephan Salzmann