10EUB Grebenzen

The start of a new era

Talstation der Ski Grebenzen Bahn in St. Lambrecht im verschneiten Gelände

The start of a new era

The 1,892-metre Grebenzen separates Styria from Carinthia and is at the same time a small but excellent ski area. Since Christmas 2022, the 10-passenger monocable gondola lift, built in record time, has carried winter guests up the mountain. The ambitious “Greben10” project opened a new chapter in the history of the ski area and at the same time created the opportunity for future summer operation.

Minimalist design, tight schedules and cost plans and the harmonious cooperation of regional companies made it possible to deliver the ropeway in just ten months. Salzmann Ingenieure was responsible for the complete handling of the project and was appointed general contractor for the construction and ancillary construction works.

Initial situation

St. Lambrecht in Styria is known far beyond the region for its more than 900-year-old Benedictine abbey. But the venerable monastery is by no means the only attraction of this municipality in the Zirbitzkogel-Grebenzen nature park. In winter, St. Lambrecht’s local mountain, the Grebenzen, turns into a ski paradise close to nature. Ski Grebenzen St. Lambrecht offers around 25 kilometres of pistes, a four-seater chairlift, 5 surface lifts and a magnificent panorama. The ski area is regarded as an insider tip away from the crowd-pullers and is particularly popular with families. Ten years ago, Lift GesmbH St. Lambrecht Grebenzen and Salzmann Ingenieure were already giving initial thought to a contemporary ropeway infrastructure with more capacity, comfort and potential for expansion. The suitable alignment was quickly found, as were the locations for the bottom and top stations. Technically, the choice fell on a 10-passenger monocable gondola lift. A pioneering and costly project like this needs to be well thought through for a comparatively small ski area. The plans were therefore put on ice for the time being.

The ropeway planner as general contractor

In the spring of 2021 the final decision was taken to build the state-of-the-art gondola lift with ropeway technology from the South Tyrolean company LEITNER. The financing was achieved thanks to the creativity and persistence of ropeway managing director Bernhard Plank and mayor Fritz Sperl. Once the necessary funds had been secured, the design was finalised and delivered in just ten months. As general contractor, Salzmann Ingenieure took on the design and financial coordination of all construction trades and so ensured absolute cost transparency. So-called cabin sponsorships played a decisive role in the financing. In close coordination and thanks to the spirited commitment of regional construction and craft businesses, the result was a project straight out of the textbook.

Technical data

System type

detachable 10-passenger monocable gondola lift

 

Length

2,810 metres

 

Vertical rise

647 metres

 

Capacity

2,090 persons/h

 

Ride time      

8 minutes

 

Maximum line speed

6m/s

 

Number of cabins    

55

 

Manufacturer

LEITNER Seilbahnen

Project
10EUB Grebenzen
Completion
2022
In collaboration with
Lift GesmbH St. Lambrecht - Grebenzen
Newsletter PDF
Download
Talstation der Ski Grebenzen Bahn in St. Lambrecht im verschneiten GeländeModerne Bergstation der Ski Grebenzen Bahn von Leitner im verschneiten GeländeBlauglas-Gondeln der Ski Grebenzen Bahn in St. Lambrecht im Winterbetrieb

Smooth delivery

Three months passed between the final go-ahead and the building application. Salzmann Ingenieure prepared the preliminary design for the architecture, structural engineering and ropeway technology, put the trades out to tender and clarified fire protection and nature conservation issues with the experts in advance. In parallel with the appointment of the contractors, the first ground investigations took place on the two construction sites. After the construction hearing and the permit on 7 July, the first excavators were already rolling in. Coherent design, optimum sequencing, punctual material deliveries, experienced companies and the committed involvement of the client in the person of managing director Bernhard Plank were the success factors – and of course good weather.

“It almost ran by itself. We were given a free hand and could play to our strengths. The open and harmonious cooperation made life easy for everyone,” reports Salzmann project manager Katrin Mangeng. The architect was able to concentrate fully on the design, while civil engineer Marie-Therese Bach always kept an eye on all the costs and reconciled them with progress on site. On site, managing director Stephan Salzmann attended to technical details at regular intervals. Client Bernhard Plank was on the construction site almost day and night and lent a hand himself together with his team.

A Christmas premiere

By the beginning of August the excavation at the bottom station was complete, the swathe for the alignment had been cleared and the floor slab of the top station concreted. Tower foundations, ducts and cables followed by September. The ropeway technology with its direct drive was then installed in the top station. In October all 17 towers along the roughly 2.8-kilometre alignment were erected, after which the rope was pulled in. Just in time for the evacuation exercise on 3 December, the operational installation was gleaming in all its glory. The authorities gave the green light as early as 20 December.

Since Christmas, guests have been making their way up to the slopes faster and more comfortably with the “Greben10” 10-passenger monocable gondola lift, built in record time. The new installation carries around 2,000 guests an hour from the valley floor up to the Grebenzenhaus restaurant at 1,654 metres above sea level. With 55 comfortable cabins, the barrier-free lift is also suitable for tobogganing and hiking and allows wheelchairs and prams to be taken along. This now also opens the door to summer operation.

Simple, efficient and cost-transparent

No additional costs, no surprises and in the end even 5 per cent under budget: the delivery of Greben10 ran like clockwork from the cost estimate to the first ride. “That is fairly rare in the ropeway industry, as there are often surprises during the construction phase,” emphasises Marie-Therese Bach. “Good planning with sufficient reserves, the client’s trust, clear decisions and good communication with one another were central to this success,” she reports. In its first-ever role as general contractor, Salzmann Ingenieure was able to appoint all the construction trades and monitor costs weekly in close consultation with the contractors.

Minimalism prevailed in the design. “A ropeway works without frills too. We concentrated on the essentials and optimised every detail,” says architect Katrin Mangeng. Carrier storage is in the bottom station, and there are exactly as many ancillary rooms as necessary. A variant with covered ropeway technology was rejected in favour of the plain design, and a mid station can be retrofitted later. Thanks to visionary design, later expansion-

stages can also be delivered efficiently. In terms of the design, ropeway operator Bernhard Plank was open to suggestions and immediately taken with the classic larch timber façade. The natural look fits harmoniously into the landscape and is at the same time a statement for this down-to-earth ski area.

Strong regional partnerships

The most transparent monitoring is worthless without reliable and punctual partners. The regional companies were exactly that from the first day to the last. No wonder, since to some extent they were also building for themselves. With the charming idea of cabin sponsorship, Bernhard Plank gave the companies a direct stake in what was happening – and in the long term at that. With their ten-year sponsorship of one cabin each, they make a significant contribution to financing the modern ropeway and advertise their business with a logo and information. “Greben 10 was and is a magnificent joint project. Everyone threw themselves into it, gave their best and made the impossible possible in the shortest time. The team spirit and the great interest in the sponsorships motivated us anew every day,” says a delighted Bernhard Plank.

The client and his team were also part of the construction crew. They were on duty almost day and night and showed real craft skills in the process. “The fact that we helped build it ourselves fills us with particular pride. We learned a lot and are all ropeway professionals now,” remarks Bernhard Plank with a smile. The first half-winter was a complete success: no incidents, satisfied guests and positive feedback from local people. It could not go any better.

Services provided in this project

All tourism services

Preliminary design

Construction supervision

Tendering

Detailed design