10EUB Senderbahn
Crossing the ski circuit by gondola

Crossing the ski circuit by gondola
Almost no waiting time from the Planai up to the Hauser Kaibling: with modern 10-person cabins, the new Senderbahn upgrades the link within the ski circuit. Since the winter of 2025 it has carried 2,400 persons per hour up to the Sender plateau in less than five minutes – in the final configuration it will be 2,800. That is twice as many as with the previous 4-person chairlift.
With the solution delivered by Salzmann Ingenieure as general planner, the ropeway also offers holiday guests a comfortable ride in summer. As the second element after the Kaiblinggratbahn, it implements the development study of 2019. Technically, the Senderbahn has everything on offer: it is ready for autonomous operation. The top station was relocated, making optimal use of the limited space on the plateau. Its roof extends the piste.
Starting point: long waiting times and little space
Hauser Kaibling, Planai, Hochwurzen and Reiteralm in the Styrian Ennstal valley combine to form the 4-Berge-Skischaukel Schladming ski circuit. Anyone wanting to cross from the Planai to the Hauser Kaibling boards the Senderbahn. Together with the Sonneckbahn opposite, it has connected the summits since 1998. At the same time it brings guests from the two lifts “Alm 6er” and Gipfelbahn back to the Sender plateau – 11 million people have ridden the 4-person chair since it opened. Over the years the numbers kept growing: in the valley guests had to wait longer, on the mountain it became more crowded. Following the analysis by Salzmann Ingenieure, the operators decided on a new build – technically state of the art, spatially optimised and also suitable for summer operation.
System type
10-person monocable gondola lift
Length
1,582 metres
Vertical rise
529 metres
Capacity
2,400 or 2,800 persons/h in the final configuration
Max. line speed
6 m/s
Number of carriers
45 or 54 in the final configuration
Ropeway technology supplier
LEITNER



Solution: comfortable transport and soon autonomous operation
Almost twice as many people now travel up to the Sender of the Hauser Kaibling quickly and sheltered from the wind in a cabin. Where the old 4-person chairlift took around seven and a half minutes to the top, the ride time is now under five minutes. This also shortens the waiting time in the valley. The high-capacity lift distributes visitor flows across the pistes more evenly and makes the transfer from the Planai easier. The ski holders on the cabins contribute to this as well.
On the basis of the development study of 2019, Salzmann Ingenieure set the required capacity at up to 2,800 persons per hour in the final configuration. The growing summer business was factored into the sizing. Operation itself is also ready for the future: LeitPilot technology from LEITNER will enable autonomous station operation in future. The Kaiblinggratbahn, built the year before, plays an important part in this. The hybrid solution for 8-person chairs or 10-person cabins, also delivered by Salzmann Ingenieure, simplified the planning, as Managing Director Stephan Salzmann explains: “This allowed us to develop an overall concept, coordinate the two top stations with one another and use the infrastructure twice over.”
The control room in the top station of the Kaiblinggratbahn serves to monitor both lifts. By managing both projects, Salzmann Ingenieure also solved the space problem on the ridge. Compared with its predecessor building, the new top station of the Senderbahn was moved around seven metres to the east. The higher boarding level allows the cabins to be stored in the basement. The roof of the carrier storage building thus acts as additional piste area. Further roof surfaces supply electricity for operation via a photovoltaic system.
Managing Director, Hauser Kaibling
Delivery: smoothly on schedule and on budget
At the Hauser Kaibling, the decision to invest in two new ropeways was taken in parallel. Salzmann Ingenieure began planning in early 2024. At the end of November the Kaiblinggratbahn celebrated its first ride. Once the construction notice for the Senderbahn had been issued, demolition of the existing installation started in May 2025. The ground-breaking followed in June, the towers were erected in August, and the ropeway technology and the stations were completed by October. After trial runs in November, the Senderbahn was ready for winter guests on 1 December.
Despite the delayed construction hearing, the build proceeded without delay: Salzmann Ingenieure monitored construction progress and costs meticulously and made adjustments where necessary. “Every trade kept to the schedule and stayed within budget. On a major project like this, that is not something to be taken for granted,” says Stephan Salzmann.
“The two new top stations have given the Sender plateau at the Hauser Kaibling a different character. As general planner we were able to implement an overall concept that works spatially and technically over the long term.” – Stephan Salzmann, Managing Director of Salzmann Ingenieure