8SB Silvrettabahn
Vorarlberg’s fastest chairlift

VORARLBERG’S FASTEST CHAIRLIFT
The planning office Salzmann Ingenieure and Silvretta Montafon GmbH have been working together successfully for a good ten years. The most recent project of this partnership is the construction of the Silvretta Bahn, which opened on 10 December 2016. The key figures of this 8-seater chairlift alone are impressive: it is over 2000 metres long and overcomes 685 metres of vertical rise in only 6.5 minutes. Given these dimensions, Managing Director Stephan Salzmann and his team faced a demanding task in the design work to comply with the prescribed standards.
The starting situation
The Silvretta Montafon GmbH ski area has for years invested with foresight in the tourism and skiing development of the destination. As early as 2006, Silvretta Nova Bergbahnen acquired the majority shareholding in the neighbouring Hochjochbahnen (Schruns). A year later, Silvretta Nova Bergbahnen AG and its subsidiaries passed into the ownership of Bank für Tirol und Vorarlberg (BTV). “Our partnership with the Silvretta Montafon ski area has existed since then, so for a good ten years. We have now accompanied and implemented five projects,” says Stephan Salzmann, Managing Director of the Bregenz planning office Salzmann Ingenieure.
The linking of the two areas Silvretta Nova and Montafoner Hochjoch in 2011 is a further significant milestone in the company’s history. “With the two gondola lifts Grasjoch and Hochalpila the area has grown together. In my view, the construction of the Panoramabahn in 2014 completed the link with a technically ideal solution,” emphasises Stephan Salzmann.
The next step in modernisation
In 2016 the Silvretta Bahn finally followed: “This chairlift provides access to one of the most beautiful ski slopes in the entire area. The pistes around the Madrisella are wide and have an ideal gradient – and are correspondingly very popular with guests,” explains ropeway planner Salzmann. The 8-seater chairlift replaced the old Garfrescha II double chairlift built in 1972. With a speed of 5.5 metres per second and a capacity of 3,200 persons per hour, the new lift takes winter sports enthusiasts straight up to the Gampapinger Berg in only 6.5 minutes. Changing to the Jöchli surface lift is no longer necessary.
Salzmann Ingenieure worked on this project – with interruptions – for several years, as the Managing Director reports: “As early as 2010 we examined initial variants, including a new alignment of the Valiserabahn via the Vermieltal. The project failed because of a lack of consent from the landowners, and attention turned in the meantime to the design and implementation of the Panoramabahn.” At first a gondola lift was under discussion as the successor to the Garfrescha II. In the end those responsible decided on a chairlift in order to optimise comfort for advanced skiers.
Technical data
8SB Silvretta Bahn (“Alptobel”)
System type
8-seater chairlift, detachable
Drive
Top station
Tensioning
Bottom station
Capacity
3,200 persons/hour
Line speed
5.5 metres/second
Drive power, operation/start-up
885 kW/1,118 kW
Number of carriers
93
Number of towers
16
Horizontal line length
1,978 m
Vertical rise
685 m
Total line length
2,151 m
Construction period
June 2016 – Nov. 2016



Carefully considered design
“The vertical rise and line length of the Silvretta Bahn are a challenge in themselves. On top of that, the terrain is relatively steep and has a lateral gradient. These conditions made the preliminary design very demanding,” Salzmann says, giving an insight into the process. “In the detailed design we fought for every metre so that we could comply with standards such as the maximum ground clearance.”
The design of the bottom station was no less demanding. It is located on the valley floor of the Vermielbach, north of the bottom station of the Vermiel Bahn. Thanks to an ingenious solution, the platform level is easy and convenient to reach. Access is from the south-east via a newly built ski route or a new ski bridge. Whichever side skiing guests arrive from, they can decide at any time whether to use the Silvretta Bahn or the Vermiel Bahn opposite.
Below the ski bridge, the basement-level depot for storing the 93 chairs fits well into the landscape. In winter the depot is barely visible anyway, and in summer the planted roof benefits the appearance of the landscape. The ropeway technology of the bottom station was enclosed with standard cladding from the ropeway manufacturer. Next to the access on the north-east side, the planners arranged a staff room with toilet. Behind it the basement conveyor is located. The architects Lang Vonier of Schruns were responsible for the architectural design.

Management Montafon GmbH
All pistes to choose from
The top station, with its single-storey service building, houses the control room with toilet, a low-voltage room as well as the transformer and storage areas. Passengers alight in the open, below the cladding for the ropeway technology. The ropeway drive, with three-phase motors, gearbox, braking equipment and emergency drive, is housed in the station frame. The station is situated at the highest point in the surroundings, so that as skiers and snowboarders alight they have all the pistes to choose from.
The chairs are equipped with weather protection bubbles and seat heating. A slip-prevention device ensures the highest level of passenger safety. The bars close automatically in the station and remain locked during the ride.