6SB Lumberjack Shuttle
Now rather than later

Now rather than later
Project start in April, construction start in July, in operation from December: the Lumberjack Shuttle –in German: Holzfäller-Bahn – in the Shuttleberg Flachauwinkl – Kleinarl ski area was built in the shortest of times. The 6-seater chairlift replaces two old surface lifts. The entire ski area is thus at the latest state of the art. As part of the “Family Run”, the new lift is especially child-safe. It also offers the perfect connection for the link to Wagrain planned for 2019.
The starting situation
The Shuttleberg ski area covers the two villages of Flachau and Kleinarl. In recent years almost the entire ski area has already been converted to detachable chairlifts. That is particularly important for the Shuttleberg’s target group, snowboarders and families with children.
Only two old surface lifts did not yet offer the desired comfort. That is also exactly where the planned connecting lift from Wagrain to Flachau will end, whose construction is planned for 2019. The Shuttleberg will then be linked to the Snowspace Salzburg, one of the largest ski areas in Austria.
With the new Lumberjack Shuttle, winter sports enthusiasts who move over to the Shuttleberg in future will find an attractive offering. “With the detachable 6-seater chairlift we have extended the alignment of the two surface lifts to the next piste,” explains Shuttleberg Managing Director Josef Harml jun. Improving comfort for families was particularly important to him: “Now we can offer child-safe transport on the longest part of our Family Run as well.” The 19-kilometre “Family Run” offers children a special experience with easy-to-ski routes.
“If it can be done, we do it straight away. That is our company philosophy." - Josef Harml jun., Shuttleberg GmbH & Co. KG
System type
detachable 6-seater chairlift
Capacity
2,600 persons/h
Horizontal length
1,922.00 m
Vertical rise
625.30 metres
Line length
2,067.553 metres
Average gradient
32.53 %
Number of carriers
89
Number of towers
17
Max. line speed
6 m/s
Ride time
6 minutes
Electrical power, operation
703 kW
Electrical power, start-up
939 kW
Manufacturer
Doppelmayr
Construction cost
EUR 9 million



Considerable time pressure
It was only in April 2017 that the owning family Harml decided to build the Lumberjack Shuttle. Salzmann Ingenieure, who had previously worked out variants for the connecting lift, were awarded the contract for the design of the detachable chairlift. The Bregenz ropeway planners examined ten variants for the Lumberjack Shuttle.
At the end of May 2017 the approval of the responsible working group of the province came through. Only then could Salzmann Ingenieure begin the detailed design. The project was submitted to the authorities as early as June. On 26 July, almost exactly five months before the planned commissioning, the construction hearing finally took place. Construction began immediately afterwards. Josef Harml jun. takes a relaxed view of the tight schedule: “If it can be done, we do it straight away. That is our company philosophy.”
Difficult ground
The geological conditions were a particular challenge: the slope along which the Lumberjack Shuttle runs moves year after year. According to geological calculations, the movement at individual towers is up to four centimetres a year. “For ground like this there are movable towers, of the kind also used on lifts on glaciers,” explains planner Stephan Salzmann.
After the first winter, no effects of the unstable ground are yet apparent. “It will probably be ten years before anything is noticeable, but with the movable towers we are prepared and have reserves for at least the next 40 years,” says Harml.
The bottom station is also located in very steep terrain at risk of slipping. Extensive stabilisation measures were necessary there too. “With a construction period of five months those are of course particular challenges “, Salzmann explains.
This short construction period was possible only with a well-practised team made up of many firms from the immediate area – likewise part of the company philosophy. Most of them have been working for the Shuttleberg ski area for years and so bring the necessary experience to the ropeway projects.
Construction was then completed as planned as early as November 2017, so that the lift went into operation punctually on 21 December.

Managing Director, Shuttleberg GmbH & Co. KG
Modern, comfortable and fast
The lumberjack lift is now the Shuttleberg’s greatest pride. It is the longest and fastest chairlift of its type in the world and overcomes the greatest vertical rise. It also has the most towers, the most powerful drive and the rope with the thickest diameter. After most of the lifts on the Shuttleberg were upgraded and improved by 2016, the entire ski area is now definitively at the newest and most modern state of the art with the Lumberjack.
But the Lumberjack Shuttle is right at the front not only in terms of technology, but also in comfort. The detachable 6-seater chairlift makes riding the lift easier above all for families with children and children’s ski groups. At the boarding point it is fitted with a conveyor belt with a lifting platform, and the self-locking child restraint ensures a safe and relaxed ride up. On the new lift one adult may take up to five small children along.