10EUB Glungezerbahn

The topic of cost efficiency

The art of investing in the right place

Guests' expectations of comfort and quality are rising, and the investment in ropeways and snowmaking is enormous. Where are savings possible, and how can tight budgets be deployed efficiently? At the Glungezerbahn south-east of Innsbruck, Salzmann Ingenieure managed the balancing act. At the Jöchle lift in the Silvretta Montafon ski area, a clever device made corresponding savings possible. Two examples of targeted investment.

The drive from Innsbruck to Tulfes takes 20 minutes. That is where the Glungezerbahn is located – ideal for day trips, for skiing in winter and for walking in summer. But when the lifts are outdated, even the very best location is of no use. In 2017 the Tiroler Tageszeitung summed up the situation: “Retro and somehow romantic, but loss-making.”

The Glungezer I double chairlift was exactly 50 years old at the time. On fine weekends skiers queued for half an hour. From the mid station, the Glungezer II surface lift took them further: likewise half a century old, with a ride time of 15 minutes. In summer it was operated as a single chairlift. The other five installations had also been in operation for more than three decades:

The ropeway company had already changed hands several times, and closure was also a possibility. In 2010 the municipality of Tulfes and the Hall-Wattens tourist board took over the company for one euro.

Only during the permit procedure was the decision taken to renew. At the top station, too, only the pitched roof was demolished, so that the toilet facilities and the piste machinery workshop could continue to be used. The ropeway technology was kept as simple as possible and the buildings realised inexpensively in timber construction. The staff of the Glungezerbahnen contributed more than 13,000 hours of their own labour in order to reduce costs.

“We did only what was absolutely necessary – but we did that properly,” describes Managing Director Höllwarth.

What was to be done? Salzmann Ingenieure drew up an overall study. The result: renewal pays off. The planning office proposed a continuous gondola lift with a mid station in place of the ancient Glungezer I and II lifts, in order to make the area attractive again all year round, above all for families.

Technical data

System type

detachable monocable gondola lift / 10-passenger cabins

‍

Capacity

960 persons/h at present, 1,600 maximum

‍

Horizontal length

1,688 metres

‍

Vertical rise

617 metres‍

‍

Slope length

1,846 metres‍

‍

Number of carriers

20 at present, 34 maximum‍

‍

Number of towers

10‍

‍

Line speed

6 m/s‍

‍

Electrical power in operation

354 kW at present, 426 kW maximum‍

‍

Electrical power on start-up

451 kW at present, 514 KW maximum‍

‍

Ropeway technology

Doppelmayr‍

‍

Electrical engineering

Frey Austria‍

‍

Construction costs

EUR 7 million

Project
10EUB Glungezerbahn
Completion
2018
In collaboration with
Glungezer Bergbahnen GmbH & Co. KG
Newsletter PDF
Download
Talstation der Glungezerbahn mit Gondel vor alpiner KulisseGlungezerbahn-Gondel im Einstiegsbereich mit „Doppelmayr“-BeschriftungGondel bei der Bergstation Glungezerbahn mit Höhenangabe „1.561 m“

High investment

The investment was, however, more than the 19 surrounding municipalities could shoulder. Years of discussion followed: “We boiled the project down and turned over every euro twice,” recalls designer Stephan Salzmann. Walter Höllwarth, Managing Director of the Glungezerbahnen, understands the owners' reluctance to put public funds into an ailing company. “But for the planning that was of course not easy.”

In 2017 all the municipalities finally gave their approval to a heavily slimmed-down phased plan worth EUR 16.5 million – five million below the first calculation. The municipalities contributed to it with a non-repayable grant of EUR 3.7 million. Instead of a continuous lift, only the renewal of the first section was envisaged for 2018, with the construction of the snowmaking system the following year. The new build of Glungezer II was not to take place until 2020 or 2021, when the financial situation allowed it again.

Hard saving

The renewal of the Glungezer I feeder lift as the first project came to EUR 7 million, also one million euros below the first calculation. A look at the detail shows how hard the saving had to be: at the bottom station, even the old ticket office and the decades-old toilet facilities were initially to be reused.

In addition, care was taken jointly to ensure that what had been deferred could sensibly be caught up later. Designer Stephan Salzmann's conclusion: “not ideal, but expedient.”

A major improvement in quality

The new 10-passenger gondola lift from Tulfes to the mid station has been running since Christmas 2018. Carrying capacity has risen by half, and long waiting times are a thing of the past. Ride time has likewise halved. The spacious carriers are also ideal for children's ski groups. In summer, prams, wheelchairs and bicycles can be carried for the first time. Salzmann's team kept precisely to the tight budget.

The first year alone was clearly above target. “We achieved a turnover that we would not even have dared to dream of,” says a highly satisfied Höllwarth. The municipalities have therefore already approved the new build of the second section: by 2021 at the latest, the installation, then 53 years old, will be replaced by a modern combined lift with 10-passenger cabins and 6-seat chairs.

Services provided in this project

All tourism services

Tendering

Construction supervision

Ongoing consultancy

Detailed design

Permit planning

Preliminary design

No items found.

Our projects

All projects