8SB Sonntagskogel II

A premium lift for the premium ski area

A premium lift for the premium ski area

SNOW SPACE SALZBURG

It does not get any better: the world’s first backrest heating, a height-adjustable conveyor belt for convenient boarding, no waiting times, beautiful descents. The Sonntagskogel II chairlift has gone from being a pure connecting lift to an attraction in the Snow Space Salzburg. Almost a million skiers used the new lift in its first winter.

‍

The starting situation

Since the merger of Bergbahnen Wagrain and Flachau in 2017, the ski areas of Flachau, Wagrain and Alpendorf St. Johann have appeared under the joint brand Snow Space Salzburg. The areas position themselves on the market as a premium ski area. Investment plans are now drawn up jointly as well.

The new construction of the Sonntagskogelbahn II was among the first projects. Until then the fixed-grip 4-seater chairlift dating from 2000 had served above all as the link between the Grafenberg and Alpendorf sub-areas. Its comfort no longer met skiers’ expectations. The installation was also becoming ever more heavily used as a result of the construction of the G-Link Wagrain. Waiting times occurred regularly when guests wanted to return from the Grafenberg to St. Johann Alpendorf.

Snow Space Salzburg AG therefore decided to replace the old installation in the very year after the merger. The aim: improvements in quality in every respect. After all, a premium ski area needs a premium lift.

“Improving the link between the areas straight away also had great symbolic significance,” explains Wolfgang Hettegger, Chairman of the Management Board of Snow Space Salzburg AG.

‍

Attractive descents

An experienced team implemented the project: the architects Hasenauer were responsible for the station buildings, and the piste design lay in the hands of AEP Planung und Beratung GmbH. Salzmann Ingenieure took on the ropeway engineering design. “Stephan Salzmann and his team have been reliable partners for us on a whole series of projects already,” says Hettegger. “Above all we value their great experience and the open exchange.”

After a thorough analysis, the proposal of the Bregenz office was: turn what was a pure connecting lift between the ski areas into a genuine attraction for skiers. To this end the ropeway planners moved the top station close to the top station of the Sonntagskogelbahn III, making the installation considerably longer. The planners shifted the bottom station only slightly, to the lowest point of all the connected pistes.

Because of the extension, a rock step had to be partly removed. Only in this way could the prescribed ground clearance be maintained. But the effort was worth it: more experienced skiers now have the choice between two attractive descents, and a ski route is available for less confident skiers.

Technical data

System type

detachable 8-seater chairlift

‍

Capacity

3200 persons/h at present, 3600 maximum

‍

Horizontal

length 620 metres

‍

Vertical rise

202 metres

‍

Line length

701 metres

‍

Ride time

2:50 minutes

‍

Number of

carriers 38 at present, 42 maximum

‍

Number of towers

11

‍

Max. line speed

5 m/s

‍

Electrical power, operation

372 kW

‍

Electrical power, start-up

443 kW

‍

Manufacturer

Doppelmayr

‍

Premium comfort

Forward-tilt function on the safety bar

Lock system

Seat and backrest heating

Convenient boarding thanks to a height-adjustable conveyor belt

Slip-prevention device

Weather protection bubble

‍

Project
8SB Sonntagskogel II
Completion
2018
In collaboration with
Snow Space Salzburg
Newsletter PDF
Download
Capacity increased

The new concept naturally also had implications for the capacity: it now had to be dimensioned so that repeat rides as well as connecting rides could be handled well. The planners opted for a detachable 8-seater chairlift. The capacity thus grew from a nominal 2400 persons per hour on the old installation to 3200 today.

That sounds like less than it is: fixed-grip installations often have to reduce speed when less confident skiers board or alight, which is why in practice they never reach their maximum capacity. In addition, the capacity of the new 8-seater chairlift can easily be increased to up to 3600 persons per hour by retrofitting five additional chairs.

‍

A comfortable ride up

For the lift itself, Snow Space Salzburg set the direction: “The new lift was, as they say in Salzburg, to pull out all the stops. The operator demanded innovations from the manufacturers,” recalls Stephan Salzmann, Managing Director of the Bregenz planning office.

Successfully so: Doppelmayr offered the world’s first backrest heating for the lift. It warms the lower back in particular. Salzmann is convinced that the technology will catch on: “That is a big plus in comfort, because skiers tend to feel the cold in the back even more than on the seat.”

Heating for the seat surface is of course also provided on the Sonntagskogel II. In addition, the installation has a height-adjustable conveyor belt which allows children, too, to board comfortably. A weather protection bubble gives protection from wind and cold.

With the opening of the state-of-the-art 8-seater chairlift, the bottleneck at the Sonntagskogel is finally a thing of the past. With the new lift we are doing justice to our positioning as a premium family ski area.
Wolfgang Hettegger, Chairman of the Board, Snow Space Salzburg
Wolfgang Hettegger

Chairman of the Management Board Snow Space Salzburg

Added safety

A second innovation combines comfort and safety. After boarding, the safety bar automatically tilts forwards a little. This draws passengers’ attention to closing the bar. This “forward-tilt function” also benefits children: they can reach and close the bar more easily.

Integrated into the chairs is also a lock system, which locks the bar once it is closed, as well as a slip-prevention device. The bar cannot be opened during the ride, and guests remain safely in their seats.

‍

Maintenance by the manufacturer

Snow Space Salzburg is also breaking new ground in maintaining the installation: a full maintenance contract covering the annual overhaul and spare parts over ten years was required as early as the tendering stage. Above all, Snow Space Salzburg expects the contract to provide cost and planning certainty.

The construction of the installation itself was standard for Salzmann Ingenieure: tendering in February, construction hearing in April, construction from May to October, commissioning in December. The result, by contrast, is spectacular: in the first winter more than 900,000 passengers used the new lift. Chairman of the Management Board Hettegger is very satisfied: “The Sonntagskogel II is currently the most innovative chairlift we operate here in the Snow Space Salzburg. A bottleneck has become a highlight of our ski area.”

‍

Services provided in this project

All tourism services

Feasibility study

Permit planning

Tendering

Detailed design

Project management

No items found.