6SB Waidoffen

A new dimension in comfort

Moderne Bergstation mit gläserner Verkleidung und Betonbau von Doppelmayr inmitten verschneiter Hochgebirgslandschaft

A new dimension in comfort

The best solutions do not always have to be spectacular or turn everything that has gone before on its head. The new 6SB Waidoffen in the Hochfügen ski area in the Zillertal proves this. “On this project our objective was to provide better access to the snow-sure mountain. In the analysis, however, we found that the existing installation was already positioned in an ideal spot,” explains Managing Director Stephan Salzmann of the Bregenz planning office Salzmann Ingenieure. “So we made the most of it.”

The starting situation

Skiliftgesellschaft Hochfügen GmbH operates five main ropeways and seven surface lifts in the Hochfügen-Zillertal ski region. The area is linked to the Hochzillertal in Kaltenbach by the Zillertal Shuttle (8EUB). The Hochfügen ski area is divided by the course of the Finsingbach into a western and an eastern part. The eastern part consists of the 6SB Holzalm and the Zillertal Shuttle. All the other installations are concentrated in the western part. Here the fixed-grip 4-seater chairlift Hochfügen 2000 served as the central repeat-ride installation. It gave access both to easy pistes and to interesting freeride slopes and was therefore always popular with guests. Less confident skiers in particular, however, had difficulties boarding the fixed-grip installation. After 24 years the lift therefore no longer met current requirements.

Technical data

System type

6-seater chairlift, detachable

‍

Drive

Top station

‍

Tensioning

Bottom station

‍

Capacity

2,600 persons/h

‍

Drive power, operation / start-up

372 kW / 468 kW

‍

Number of carriers

58

‍

Number of towers

11

‍

Horizontal length

1,011 m

‍

Vertical rise

317 m

‍

Total line length

1,097 m

‍

Construction period

June – November 2016

Project
6SB Waidoffen
Completion
2016
In collaboration with
Skiliftgesellschaft Hochfügen GmbH
Newsletter PDF
Download
Bergstation Waidoffen von obenModerne Bergstation eines Sessellifts im Schnee mit Alpenpanorama

Considered design

“In order to increase comfort and safety for guests, we designed a detachable 6-seater chairlift,” reports Stephan Salzmann. The route of the lift has essentially remained the same: the bottom station lies in the area of the Lamarkalm Hochleger, the new top station on a ridge north-west of the Pfaffenbichl. Even the capacity rose only moderately with the new installation, from 2,388 to 2,600 persons per hour, because the analysis of piste capacity showed that a higher capacity would be at the expense of comfort and safety on the piste, despite improvement measures.

Rapid construction despite redesign

In Hochfügen the so-called “D-Line” from Doppelmayr was used as a chairlift for the first time anywhere in the world, and it was also the world premiere for the new CONNECT control system. “The installation had been fully designed and already submitted to the authorities. When Doppelmayr presented us with the D-Line, a world first, we could not refuse this premium product,” reveals the Managing Director of the ropeway company, Helmuth Grünbacher. “The decision in favour of the new system was taken only shortly before construction started. We had to adapt the plans to the new technology in the shortest possible time,” Salzmann adds. “Because we handle the entire design process in house, we mastered this challenge too. We were able to push the construction through in barely five months: the start was at the end of June 2016 and the official acceptance inspection took place on 22 November 2016. The chairlift went into operation the following day.”

New standards in technology and safety

The installation offers the current state of the art in comfort and safety: the safety bars close fully automatically after boarding and unlock only on entering the top station. The individual seats are considerably wider than standard models and ergonomically shaped. The integrated seat heating and weather protection bubbles make for a comfortable ride up even in bad weather. A gearless direct drive is used, distinguished by low maintenance requirements and high efficiency.

Old and new complement each other

To save costs, parts of the old bottom station were integrated into the new building. They house the power supply, storage and the staff rooms. The ropeway technology is housed in the newly built hall, as is the access to the staff room and a public toilet facility with anteroom. The chairs are stored in a loop depot arranged to one side. The hall is a structure of precast concrete elements, combining a high-quality appearance with rapid construction and low cost. The existing building was also clad with coloured precast concrete elements and thus blends visually into the new building.

For the new top station the lift axis was swung towards the east in order to accommodate the larger structures better. The building has two storeys. The basement contains the transformer installation, a service water reservoir and a storeroom. On the ground floor, in addition to the control room, there are the low-voltage room, a staff toilet and a room for piste rescue. This structure was also built in coloured concrete and fits very harmoniously into the rocky mountain landscape.

The unloading area is now more generously dimensioned. In conjunction with the piste corrections in the upper section, this results in a comfortable unloading situation. The gentle gradient makes it easier for beginners to move off into the terrain. The top station is also equipped with a highly efficient photovoltaic system which generates energy all year round with an output of 12 kWpeak and feeds it into the grid. The solar elements are integrated into the station roof so that they blend elegantly into the appearance of the building and the landscape.

Services provided in this project

All tourism services

Feasibility study

Preliminary design

Permit planning

Detailed design

Tendering

No items found.

Our projects

All projects