8EUB Schatzbergbahn
The long wait is over

The long wait is over
A tight schedule, a tight budget: the renewal of the Schatzbergbahn in the Ski Juwel Alpbachtal Wildschönau was a particular challenge for Salzmann Ingenieure. In a good six months the Bregenz planning office carried out the renewal of the 32-year-old gondola lift. To keep within the budget, existing infrastructure had to be integrated into the new installation. At the opening, punctually for the start of the winter season, there was every reason to celebrate: the planned construction costs were met.
The starting situation
The Tyrolean ski area of Schatzberg in Auffach, together with the Alpbacher Bergbahnen, forms a large interconnected ski area known as “Ski Juwel Alpbachtal Wildschönau”. For 32 years the 4EUB Schatzbergbahn was the only feeder lift bringing guests into the ski area from Auffach – at four kilometres long, one of the longest gondola lifts in Austria. Skiers also used it as a repeat-ride installation, as the available piste areas are very extensive and appealing.
Although it was in technically faultless condition, the operators had wanted the installation renewed for years. The reason was its insufficient capacity of a maximum of 1600 persons per hour – too little for up to 5000 first entries a day in the high season. To bring these guests into the ski area, the former gondola lift needed an average of four hours. Waiting times of up to 50 minutes at the bottom station were the result – a test of patience that fewer and fewer guests were willing to endure.
Because of this overloading, only a few repeat riders used the lift, especially in the morning. Owing to its length of two kilometres, guests also hardly used the parallel surface lift any more and avoided the attractive pistes. The whole installation was literally on the ropes
System type
8-passenger monocable gondola lift with mid station, capacity 2,650 persons/h
Line length
4,061 metres
Vertical rise
912 metres
Average gradient
23.41 %
Number of cabins
142
Max. line speed
6.0 m/s
Ride time
13 minutes
Electrical power
1,143 kW
Manufacturer
Doppelmayr
Construction cost
EUR 18 million



Success with “snow-how”
The best proposal for renewing the installation came from the Bregenz planning office Salzmann Ingenieure, with its “snow-how” from 350 completed ropeway projects. “When we received the enquiry in 2013, the client’s wish was clear: to increase capacity and comfort significantly at the lowest possible cost,” recalls Managing Director Stephan Salzmann.
“For us the conclusion was therefore equally clear: we had to continue using as much of the existing infrastructure as possible.” Salzmann Ingenieure examined alternatives such as a retrofit of the existing installation, alternative system types and also relocating the station sites. In the end the requirements could best be met with a modern detachable monocable gondola lift with cabins for eight passengers.
When the investment decision was taken in 2016, the cost estimate for the four-kilometre lift and the renewal of the three stations finally came to 18 million euros. To keep within the tight budget, the basement levels of the bottom, mid and top stations had to remain. This allowed existing infrastructure such as three transformer stations, two pumping stations, snowmaking equipment, offices and ski rental to continue in use. The existing alignment also remained almost unchanged. Escalators were planned in the bottom station and a ramp in the mid station, in order to bring guests comfortably from the piste up to the higher-level platform.
The top station, including the platform with access and exit as well as a new area for putting on skis, was newly built to the north of the existing structure. The storage depot was accommodated on the existing basement level. The cabins are now stored in the bottom and top stations in a ground-level stub-track depot with a maintenance loop. The haul rope runs over both sections, with the drive located in the top station for rope-static reasons. The haul rope is tensioned in the bottom station.
The construction work at the bottom station brought an unpleasant surprise. Contrary to the initial calculations, the structural capacity of the basement level did not permit a superstructure. Salzmann Ingenieure quickly found a solution: around half of the former basement level was removed, while the other half is spanned by a new steel structure.
“A situation like that is of course a huge challenge. It takes the greatest flexibility from everyone involved,” recalls Stephan Salzmann. There was at least one positive side effect: the ticket offices and toilet facilities were now renewed as well. “Despite this additional work we were able to keep to the planned construction costs,” Salzmann is pleased to report.
Delays? Not with this lift!
The second major challenge besides cost was the time pressure. Although the submission was made on schedule, the construction hearing took place only a month late. The ground-breaking finally took place on 20 May 2017 – just six months before the planned commissioning. Doppelmayr as supplier of the installation and the many local specialist firms did an excellent job: thanks to their speed and competence the schedule was met after all.
The craftspeople’s work also made traditional values visible: the retention of the pitched roofs and the use of local timber now show a good mixture of sustainability and modernity.
On 8 December 2017 the new Schatzbergbahn finally went into operation on time. The new lift has brought the hoped-for effects: there are hardly any waiting times at the bottom station any more, and the pistes are used considerably more. Guest satisfaction has risen significantly.