8EUB Golmerbahn conversion

Modernisation during ongoing operation

Modernisation during ongoing operation

Since 1995 the Golmerbahn has carried countless winter and summer guests up to 1,893 metres above sea level into the Montafon ski and hiking area below the Golmer Joch. After 25 years, the operator Golm Silvretta Lünersee Tourismus wanted step-free and comfortable boarding on the monocable gondola lift. To that end, by December 2022 the old eight-passenger cabins had been replaced with state-of-the-art models, boarding levels adjusted, lifts installed and unforeseeable problems solved. The architecturally demanding modernisation was achieved without any break in operation, in four time windows between the seasons.

‍

Initial situation

With nine lifts, a forest rope park, a flying fox, an alpine coaster and a forest slide park, the Golm adventure mountain in Vorarlberg’s Montafon valley is one of the most versatile ski and hiking areas in the province. Its heart and main feeder into the mountains of the Rätikon is the Golmerbahn. In 1995 this eight-passenger monocable gondola lift succeeded the inclined lift that had been in operation from 1959. Over three sections, 34 towers and almost 4 kilometres it runs from the bottom station in Vandans via the intermediate stations in Latschau and Matschwitz to the Grüneck top station.

Originally, 127 cabins carried up to 1,800 persons per hour. What was state of the art at the time of construction can no longer reasonably be expected of guests today. After 25 years in service, the operator Golm Silvretta Lünersee Tourismus therefore looked for a step-free alternative to the old carriers and found it at Doppelmayr. Initial test runs confirmed that the popular OMEGA IV cabins were in principle suitable on the existing grips with different hanger arms. The new carrier models were to allow boarding at platform level in future (level walk-in).

The ropeway buildings erected in 1995 were designed by architect Leopold Kaufmann and artist Karl-Heinz Ströhle. Shingled glass façades and the colour scheme of the timber ceiling structure, which changes from station to station, create a light-filled atmosphere. In the structural adaptations, this aesthetically demanding architecture had to be preserved just as it did in the installation of lifts. Salzmann Ingenieure was responsible for the applications, the tendering of the individual trades, the local construction supervision and thus for converting the lift as quickly as possible.

‍

Technical data
Project
8EUB Golmerbahn
Completion
2022
In collaboration with
Golm Silvretta Lünersee Tourismus GmbH
Newsletter PDF
Download
Conversion under time pressure

In winter and in summer the Golmerbahn carries thousands of guests uphill every day. Year-round operation therefore left only short time windows for conversion work between the seasons. To make the best possible use of the five weeks in total after Easter and in the autumn, meticulous planning and coordination were required. Because the iconic building by Kaufmann and Ströhle was to keep its unmistakable profile, the renowned firm BHP Baumschlager Hutter Partners took on the architectural design.

In the course of the modernisation, platform levels, running ways and carrier storage were adapted and lifts installed in the intermediate stations. A piste machine garage and a refuse room were added. Two construction stages were planned at the outset – unexpected additional work and supply bottlenecks turned these into four. Salzmann Ingenieure showed flexibility, coordinated closely with the trades and arranged partial permits for the ropeway and garages, the lifts and the refuse room. The construction areas were temporarily sealed off. In this way safe and uninterrupted public operation was achieved.

‍

Gentle modernisation with a strong effect

A clear run for everyone: since the spring of 2022 the Golmerbahn has been carrying its guests, including those with a wheelchair or pram, comfortably and barrier-free from Vandans to Grüneck. The 110 contemporary eight-passenger cabins have replaced their 127 slightly smaller predecessors and, thanks to level walk-in, have made the journey up the mountain easier for passengers ever since. Despite the extensive adaptations, the transformation is barely noticeable. “What we wanted was the gentlest and most efficient possible modernisation of the ropeway technology. With comparatively simple means, this careful solution creates maximum comfort for all our guests and also preserves the architectural and artistic character,” emphasises Markus Burtscher, Managing Director of Golm Silvretta Lünersee Tourismus.

For step-free boarding, the grating floors and lifting platforms in all four stations were raised by seven centimetres. Two lifts in each of the Latschau and Matschwitz intermediate stations, previously accessible only by stairs, now provide barrier-free access to the platform. What sounds simple had its pitfalls. These were mainly structural in nature and in part hidden beneath concrete, as project manager Jörg Egger reports: “In Latschau we had to cut channels into the concrete and first record the existing structure precisely with a 3D scan. The steel structure at Matschwitz rests on a system of columns and struts. We had to think very carefully about what we touched, where and how.” In this, Salzmann Ingenieure was able to rely on the structural engineering specialists of the gbd group from Dornbirn.

‍

The new Golmerbahn combines international design with the very highest level of ride comfort. Switching to contemporary ropeway technology without interruption and without major structural change is a perfect example for responsible, environmentally sound infrastructure projects in tourism.”
Markus Burtscher

Managing Director, GSL

Maximum freedom of movement

In Latschau, concrete cutting work was on the agenda alongside raising the levels. So that the sections can be operated individually, a folding carrier guide was included in the design. In the folded position this needs space, and that space was not available. “So that the cabins can move, we had to lower the surface by a few centimetres in some places,” reports Jörg Egger. Changes were also needed in the garage, where a new lifting platform was built.

Before the first parts could be cut out of the concrete, the situation had to be examined carefully. “We did not know where the cables and pipes ran and which walls were load-bearing. The old drawings contained no exact information,” explains the project manager. Because the “Holzschopf” restaurant and a transformer station are located directly beneath the boarding level, the greatest care was called for. Together with gbd, the existing structure was surveyed by 3D scan and a structural analysis carried out. After the trial drilling, some ceiling elements were removed and re-concreted, others cut out. Additional steel reinforcements and columns provided stability.

In building the lift on the downhill side, parts of the concrete floor were removed and the lift’s emergency drive relocated. Oil lines and pipes had to be extended for this – no trivial matter during operation. The second lift was built as an extension next to the stairs, and the shingled glass façade and the timber ceiling were continued seamlessly. Such an imitation was originally also planned for the façade of the new piste machine garage on the green field next door. For fire and avalanche protection reasons, however, it was built as a plain concrete cube – regulations are regulations. Salzmann Ingenieure converted the previous garage in the basement of the building into refuse and storage rooms by means of an intermediate ceiling and a goods lift.

‍

Safe comfort on stilts

Raising the platform level and the lifting platforms in the Matschwitz intermediate station at 1,521 metres above sea level was particularly complex, because this all-steel structure stands on stilts. The unusual construction of the building made the raising work many times trickier than with a concrete floor. For Jörg Egger and the Salzmann Ingenieure team, the filigree forest of struts raised structural questions above all: where do we intervene? Where do we remove material? What are the effects on the overall structure?

In close coordination with the experts at gbd and a committed steelwork crew, the platform plateau was raised by the required seven centimetres within a few weeks. Thanks to the precise survey of the existing structure, no visible traces remain. “The new steel elements do not differ in colour from the original,” reports Egger. For the construction of the passenger lifts on both sides, a break room and a WC were also demolished and rebuilt elsewhere. As in Latschau, the two lifts fit harmoniously into the overall architectural fabric.

‍

‍