60PB Grünberg Seilbahn

A new ropeway despite resistance from local residents

Grünberg-Seilbahn in Gmunden bei sonnigem Herbstwetter

A new ropeway despite resistance from local residents

The Grünberg ropeway exceeded all expectations in its very first season of operation: more than 100,000 guests have already travelled on the twin-track aerial tramway. Yet for a while it was doubtful whether the project could be realised at all, because landowners tried vehemently to prevent construction. The clients and Salzmann Ingenieure persevered, however, and were ultimately able to build the ropeway as planned.

Planning for the new Grünberg ropeway began back in 2009. Until then, a bicable gondola lift with 24 cabins had carried passengers up the Grünberg by the Traunsee in Upper Austria. The installation had been in operation since 1954, however, and was correspondingly outdated. Not least because of the measures following the accident in 2004, the expenditure on maintenance rose continuously.

“The Grünberg nature recreation area is a popular destination for excursions in our region,” explains the Managing Director of Oberösterreichische Seilbahnholding GmbH, Alfred Bruckschlögl. “That is why it was very important for us to be able to carry our guests comfortably and safely once again.” In the course of the relaunch project, a wide variety of leisure facilities were created, such as a summer toboggan run, cycling and mountain bike trails and a low rope course.

‍

Alignment retained

The clients commissioned Salzmann Ingenieure for the design and implementation. At the outset the Bregenz engineers examined whether it would make sense to change the course of the Grünberg ropeway. After weighing up costs, the prospects of obtaining a permit and the benefits, the clients decided to retain the existing alignment and to optimise the station locations.

Technical data

System type

Twin-track aerial tramway

‍

Drive station

Top station

‍

Haul rope tensioning

Bottom station

‍

Rope track gauge

0.9 to 10.25 m

Bottom station elevation

435.75 m a.s.l.

‍

Top station elevation

986.64 m a.s.l.

‍

Horizontal line length

1,949.13 m

‍

Average gradient

28.26 %

‍

Slope length

2,030.71 m

‍

Capacity

607 persons/h

‍

Number of carriers

2

‍

Persons per carrier

60+1

‍

Number of towers

2

‍

Line speed

10 m/s

‍

Max. power (start-up)

593 kW

Project
PB Grünberg Seilbahn
Completion
2014
In collaboration with
Oberösterreichische Seilbahnen Holding GmbH
Newsletter PDF
Download
Grünberg-Gondel in der Bergstation vor der AbfahrtBergstation der Grünberg-Seilbahn mit Wanderern im HerbstModerne Konstruktion der Grünberg-Bergstation aus Glas und Stahl

Twin-track aerial tramway with two cabins

Unlike in ski operations, the capacity required on the Grünberg is not so high. The ropeway is used almost exclusively by day visitors. At certain times of day, after midday for example, demand is quite high, while at other times of day passenger numbers are lower. Salzmann Ingenieure recommended an aerial tramway with two cabins for sixty persons each, as this system can be operated cost-effectively given the requirements. “At peak times we can carry twice as many people as before,” explains Salzmann. “Introducing a flexible timetable makes it possible to cover the varying demand.”

‍

Resistance from the landowners

When the project operator first presented the construction scheme in 2010, there was strong resistance from the landowners. “We met the local residents for further negotiations and presented them with the current status of the project each time,” reports Salzmann. “That allowed us to listen to their concerns and, where possible, to take them into account in the next design steps.”

The landowners demanded that the width of the new alignment should not exceed that of the existing one. A challenge, because the new cabins are designed for sixty persons and the existing ones for four. “We nevertheless found a solution and reduced the track gauge in the bottom station to the absolute minimum of 90 cm. As the point where the carriers pass each other lies high up in rope span 1, this extreme line routing was possible,” reports Salzmann. In this way the local residents' requirements for the clearance profile could be met.

At the beginning of 2011 Salzmann Ingenieure presented the plans again. “Although the narrowing of the alignment we proposed even brings improvements for most local residents compared with the existing ropeway, a few particularly stubborn opponents still did not agree at first,” explains Salzmann. Further negotiations and discussions followed.

Expropriation possible

‍

As the Grünberg is an important attraction for tourists and locals alike, implementing the project was also in the public interest. Representatives of the town supported the scheme. Legally, under the Railways Act, expropriation of the owners would even have been possible. When this realisation filtered through to even the most embittered opponents, all the landowners finally agreed to the project in mid-2012.

Because of the delay to the building permit, the manufacturers no longer had long-lead components such as the gearbox in stock. The ground-breaking therefore did not take place until spring 2013. The top and bottom stations were demolished and rebuilt; the plans for them came from Salzmann Ingenieure. The new top station was moved down the mountain and blends discreetly into the landscape. The building in the valley, by contrast, is urban and strong in design. As a catering business directly adjoins the bottom station, an optimised method of construction had to ensure that no noise would later be transmitted into the catering business's building.

In early summer 2014 the ropeway was able to open: instead of the expected 40,000, more than 100,000 people have already travelled on the Grünberg ropeway. “The efforts have paid off completely,” reports Bruckschlögl. “The feedback is very positive. A ride on the fully glazed Grünberg ropeway with a view over the Traunsee is a great experience for our guests.”

Services provided in this project

All tourism services

Preliminary design

Tendering

Detailed design

Permit planning

No items found.